Intratrek overpaid: Gumbo

By Sukulwenkosi Dube-Matutu

Energy and Power Development Minister Dr Joram Gumbo has said Intratrek Zimbabwe Private Limited, a company owned by Harare businessman Mr Wicknell Chivayo, which was paid $5 million for the Gwanda Solar Project, may have been overpaid.

Energy and Power Development Minister Dr Joram Gumbo
Energy and Power Development Minister Dr Joram Gumbo

Speaking in an interview during a visit to the site on Thursday, Dr Gumbo said his ministry would submit a proposal to the Government on how best the project could be implemented.

Intratek Zimbabwe Private Limited was awarded the tender in 2015 and was paid $5 million by Zimbabwe Power Company (ZPC) to build the 100-megawatt Gwanda Solar Power Plant.

After receiving the money without a bank guarantee, no meaningful development has taken place at the site.
“I’m here at the Gwanda Solar Project site on a familiarisation tour. There has been a lot of talk surrounding this project which was awarded to Intratrek with a total amount of $5 million being paid to the company for pre-commencement works.

“I need to have a clear understanding of what really transpired as I understand that the matter is now before the courts.

“My interest is for the project to take off because one way or the other, Government has to make a decision for the project to take off.

“I have requested a detailed report on the project from the Zimbabwe Power Company (ZPC).
“After receiving the report, I will sit down with my team and come up with recommendations which we will submit to Government on the way forward,” Dr Gumbo said.

Related Articles
1 of 92

He expressed disappointment as no work has been done at the site of the project despite the $5 million payment that was made to Intratek.

Dr Gumbo said the solar project was a crucial initiative that would not only benefit the Matabeleland region, but other areas as well.

He said the project had been divided into three phases and the first one was supposed to have been completed by now.

Dr Gumbo said the work that had been reportedly done at the site so far such as clearing of the land was sub-standard.

“I’m told that $5 million was paid for preliminary works, but I’m questioning whether it (Intratek) wasn’t overpaid.

“I say so because there is a similar project in Mutoko where $2,4 million was spent on a solar project and it’s already producing power. It also has proper infrastructure compared to this bush which hasn’t been properly cleared.

“This is a big project that is supposed to produce 100 megawatts. People have been waiting for this project since 2015 as it is one of the biggest projects we will have in Matabeleland region.

“We will evaluate the project and the required time frames and come up with a plan. We want to see this project taking off,” he said.

A ZPC official on the ground who preferred anonymity said some of the works which should have been completed during the pre-commencement stage comprised clearing of 200 hectares of land, fencing, construction of three temporary structures, drilling of a borehole, establishment of a quarry, tarring of 2,4 kilometres of road and a water and sewer system.

He said so far half of the site had been fenced, 70 hectares of the land had been cleared and two temporary structures built.

Two-hundred-and-sixty hectares of land was aside for the project. The Herald.