Gwayi-Shangani Dam construction on course

Must Try

Trending

By Leonard Ncube

Construction of the Gwayi-Shangani Dam in Matabeleland North is well on course with 34 percent of work done and the contractor hopeful to meet the December 2019 target for completion.

This follows allocation of $23.33 million by Treasury in the 2018 budget, although the contractor has complained about delays in disbursement of the funds to acquire material.

China International Water and Electric Corporation is the contractor in partnership with the Zimbabwe National Water Authority (Zinwa).

Briefing the Minister of State for Matabeleland North Provincial Affairs Richard Moyo during a tour of the dam site yesterday, Zinwa assistant resident engineer Brian Musarurwa said most of the preliminary work had been completed.

He said the dam wall will be 72 metres high and 4 metres will be completed in December before the rains start. “We are building the wall in blocks and we expect to have finished four metres in December. We will stop when the rains start but the design allows us to continue with work even if it’s raining.

“We had planned to construct to a height where we wouldn’t be disturbed by the rains but unfortunately due to delays in funds disbursements and foreign currency constraints we received some of the materials late hence we have not been able to reach that height,” said Eng Musarurwa.

He said the major component of construction work which include excavation of the foundation was done, with about 9 000 cubic metres of concrete already poured for footing.

“We are raising the dam wall now and we are at an average of three metres because we are building in blocks but by December we anticipate we will be at an average of four metres high.

Rains will indeed disturb work but we will then shift to constructing outlets on the river bank until water subsides,” said Eng Musarurwa.

He said he was happy with progress so far.

“We may have been facing some challenges but we received most of the materials required in August and within a month we have managed to do much work.

We are capacitated now and technically we are still able to finish this dam by December 2019 because raising the wall is actually easier,” added Eng Musarurwa.

Minister Moyo said the project will benefit communities through provision of water for consumption and irrigation and creation of a greenbelt between the Zambezi and Bulawayo.

“The project will benefit our agricultural sector through irrigation and also the communities thereby raising standards of living. Let’s us all work together so we make Matabeleland North the best in terms of development,” he said.

The total cost of the project is $121 732 922,60 and it is viewed as the panacea for water challenges in Bulawayo and the Matabeleland region.

A pipeline will connect from Zambezi River via the dam to Cowdray Park water works in Bulawayo with multiple outlets along the way where various projects will be carried out to create a greenbelt. The Chronicle.

Related Articles

The Kariba Dam supplies 2,010 megawatts of electricity to parts of both Zambia (the Copperbelt) and Zimbabwe and generates 6,400 gigawatt-hours per annum. (Picture via Manfidza, CC BY-SA 4.0 , via Wikimedia Commons)

El Nino’s shadow looms large: Kariba Dam at risk as water levels plummet

0
The Zambezi River Authority (ZRA) has issued a stark update on the water situation at Kariba Dam, revealing a concerning decline in river flows and lake levels.
The Kariba Dam supplies 2,010 megawatts of electricity to parts of both Zambia (the Copperbelt) and Zimbabwe and generates 6,400 gigawatt-hours per annum. (Picture via Manfidza, CC BY-SA 4.0 , via Wikimedia Commons)

El Niño threatens future of power generation in Zimbabwe and Zambia

1
The Zambezi River is experiencing a worrisome dry spell, resulting in the uncertainty of the future of power generation in Zimbabwe and Zambia. The Zambezi River Authority (ZRA), responsible for managing the river's resources for the two countries, said it is closely monitoring the situation.
Zimbabwe National Water Authority (ZINWA) head of corporate communications Marjorie Munyonga (Picture via LinkedIn - Marjorie Munyonga)

Zimbabwe water authority frets over dwindling dam levels as El Nino strikes

1
The Zimbabwe National Water Authority (ZINWA) has urged farmers to use dam water sparingly to delay the depletion of the resource which is dwindling due to the dry spell that the country is experiencing.
Construction of the Kunzvi Dam, which is expected to solve Harare’s water challenges, is progressing well with excavation works currently underway.

Kunzvi Dam now 36 percent complete… set to alleviate Harare water woes

0
Construction of Kunzvi Dam in Mashonaland East province, which is touted as the panacea to the water challenges that the city of Harare faces is on course with the project now 36 percent complete, an official has said.
Hwange Colliery

52 families face eviction in Binga to allow Hwange coal mining

1
A total of 52 families in Lubimbi, Binga, Matabeleland North are facing eviction after Hwange Colliery Company got a grant to extract coal from the area.

Don't miss a story

Breaking News straight to your inbox.

No spam just news !

0 0 votes
Article Rating
Subscribe
Notify of
0 Comments
Oldest
Newest Most Voted
Inline Feedbacks
View all comments
Donate to Nehanda Radio

Latest Recipes

Latest

More Recipes Like This